(916) 802-5127 Get pricing

CFE guide · Invoicing and getting paid

Bill Stored Material on a Progress Invoice

On a progress invoice, click Stored material to bill material that is delivered but not installed yet. BidWise shows what is in the warehouse for the job, here 4 lines and $72,251.04 at cost, about $53,269.63 at bid price. Type what is stored on each line, or click Put it on the first line. When it is installed, bill it as % complete and lower the stored amount; the invoice bills only the change.

  • 5 minutes
  • Intermediate
  • CFE BidWise Business
CFE BidWise Stored material for Valley Fitness Center: warehouse 4 material lines received, $72,251.04 at cost, about $53,269.63 at bid price
Video walkthrough · 4:10 · Guide 96 of 100

Why bill stored material?

On a big job, the material can be most of the money, and it sits in your warehouse for weeks before it goes down. Until you bill it, you are paying for it and the GC is not.

Most GCs allow stored material on the pay application. BidWise knows what came in for the job, so the number is ready when you bill.

The five steps

  1. Start a progress invoiceProgress billing, % complete.
  2. Read the linesContract, billed before, left to bill.
  3. Open Stored materialWhat is in the warehouse.
  4. Type what is storedPer line, or put it on the first line.
  5. What can go wrongNothing shows in the warehouse.

1Start a progress invoice

CFE BidWise new invoice INV-1005 for Valley Fitness Center: bill to Harborline Construction, invoice date 11/19/2026, net 45, GC job SC-2655, billing period 11/11 to 11/19/2026, salesman Ana Ruiz, retainage 10%, progress billing % complete
INV-1005 for Valley Fitness, Progress billing, % complete.

On the Invoicing tab, click New invoice and pick the job, here Valley Fitness Center, JR-260106. The GC, Harborline Construction, the GC job number, the salesman and Retainage 10% fill in from the job.

Under How do you want to bill?, click Progress billing, % complete.

2Read the lines from the estimate

CFE BidWise progress invoice lines: base bid contract $293,730.22, billed before 40%, $117,492.09, left to bill $176,238.13; extra work EW-002 $1,236.60; totals contract $294,966.82
Contract, billed before, % complete to date, and left to bill.
CFE BidWise job billing so far: contract $294,966.82, invoiced to date $105,742.88, paid $105,742.88, owed $0.00, retainage held $11,749.21, left to bill $177,474.73
Job billing so far: $177,474.73 left to bill.

The lines come from the estimate: Base bid, $293,730.22, billed 40% before, and Extra work EW-002, $1,236.60. You type the % complete to date, and only sell prices show: costs, labor and margins never show on an invoice.

On the right, Job billing so far: contract $294,966.82, paid $105,742.88, retainage held $11,749.21, and $177,474.73 left to bill.

3Open Stored material

CFE BidWise Stored material for Valley Fitness Center: price stored material at bid price, warehouse 4 material lines received $72,251.04 at cost, not installed yet about $53,269.63 at bid price, put it on the first line
4 lines in the warehouse: $72,251.04 at cost, about $53,269.63 at bid price.

Next to Stored material (column F), click + Stored material. The box says what BidWise knows: Warehouse: 4 material lines received, $72,251.04 at cost. With the job 40% billed, about $53,269.63 at bid price is not installed yet.

Price stored material at is Bid price, what the GC pays for it. Pick cost instead if the GC’s contract says so.

Quick Tip

Send the GC the delivery tickets and a photo of the material in the warehouse with the pay app. Most GCs will not pay stored material without proof it is there and insured.

4Type the stored amount, and save

CFE BidWise Stored material lines: base bid last application $0.00, room left $176,238.13, stored now; extra work EW-002 room left $1,236.60, stored now; Cancel and Save
Stored now, per line, up to the room left.

For each line, type the Stored now amount, up to the Room left: the base bid has $176,238.13. Or click Put it on the first line to put the $53,269.63 on the base bid.

Click Save. The invoice adds the stored material to This invoice. On the next one, when it is installed, bill it as % complete and lower the stored amount; the invoice bills only the change.

5What can go wrong, and how to fix it

CFE BidWise progress invoice: stored material column F, material delivered to the site or warehouse, not installed yet, none, plus Stored material
Stored material (column F): delivered, not installed yet.

The warehouse shows nothing. Only material received on the job counts. Check the deliveries in on Receive.

Billed twice. When the material goes down, raise the % complete and lower the stored amount by the same value. The total billed stays right.

The GC rejects it. Some contracts do not allow stored material, or only at cost. Check the contract, and change Price stored material at.

Worked example: Valley Fitness Center, INV-1005

Jordan bills Valley Fitness on November 19:

LineAmount
Material in the warehouse, at cost$72,251.04
Not installed yet, at bid priceabout $53,269.63
Stored now, on the base bid$53,269.63
Less 10% retainage$5,326.96
Stored material on this invoice, net$47,942.67

The money for the material comes in before the crew puts it down.

What to do next

That is the last guide for now. See every guide.

Get paid for material before it goes down

Progress billing is part of CFE BidWise Business. Start with the 30-day free trial, no credit card.

Download Free for Windows64-bit · 30-day free trial · no credit card

Frequently Asked Questions

What is stored material?

Material delivered to the site or your warehouse for the job but not installed yet. On a pay application it is column F.

At cost or at bid price?

Bid price by default, what the GC pays for it. Pick cost if the contract says so.

What happens when it is installed?

Bill it as % complete and lower the stored amount by the same value. The invoice bills only the change.

Cristian Valcu, founder of Commercial Flooring Estimating LLC

Written by

Cristian Valcu – Founder & CEO, Commercial Flooring Estimating LLC

Cristian has estimated commercial flooring for over 20 years and built CFE BidWise around the way flooring contractors actually price, propose and track their bids.