CFE guide · Accounting
Holdback and Lien Deadlines, Job by Job
Open Accounting › Holdback & liens. Every Won job shows the holdback held, the day it was completed, the lien deadline and the day the holdback comes due back. In British Columbia that is 10% held, a lien within 45 days of completion and the holdback paid out after 55 days, so you collect what you are owed before your lien rights run out.


Why watch holdback and lien days?
On a Canadian job the owner or the general contractor keeps back 10% of every payment. On a $400,000 floor that is $40,000 of your money waiting until the job is done. It is also the clock on your lien rights: miss the lien deadline and the only way left to collect an unpaid invoice is a lawsuit.
CFE BidWise counts the days for every Won job from the completion date, so the office sees which job needs a phone call this week and which holdback can be billed today.
The six steps
- Open Holdback & liensAccounting › Holdback & liens.
- Read the datesCompleted, lien deadline, due back.
- Check your province’s daysAccounting › Settings.
- Set the completion dateThe clock starts here.
- Holdback on every invoiceHeld on progress, billed on release.
- What can go wrongLate deadlines, wrong dates.
1Open Holdback and liens

On the Accounting tab, click Holdback & liens. The note at the top states the rules for your province. In British Columbia, owners and general contractors hold back 10% of each payment, you can file a lien within 45 days after completion, and the holdback is paid out after the 55-day holdback period.
The tiles add it up. Northgate has $150,647.79 of holdback held on 4 jobs, and every job of $100,000 or more needs a holdback account.
2Read the dates on each job

Each row has the Completed date, what is Owed to us, the Lien deadline and the day the Holdback due back. The list is sorted by the deadline, so the job with the least time left is on top.
Lincoln Elementary was completed on September 26. Every invoice is paid, so its lien deadline just says paid, and its $39,984 of holdback comes due back on November 20. Cedar Park Senior Living still owes $101,907.48, and its lien deadline is December 4, 15 days away.
3Check the holdback and lien days for your province

Click Holdback and lien days, or open Accounting › Settings. The province fills in Holdback on progress invoices, the Lien deadline in days after completion and the Holdback period. Change one with the pencil if your contract or your lawyer says otherwise.
Ontario and Quebec work the same way with their own days. In Quebec the page talks about a legal hypothec instead of a lien.
4Set the completion date

Left blank, CFE BidWise uses the last job cost or invoice date as the completion date. When the job is really done, click Completion on its row and type the Last day of work or delivery, or the date on the certificate of completion. Both clocks move with it.
The same window keeps the lien waivers you give, conditional or unconditional, progress or final, each with its date.
Type the completion date the day the job is done. A date that is too late makes the deadline look further away than it really is.
5See the holdback on every invoice, then bill the release


Every progress invoice takes the holdback off before the GST. On invoice 1005 for Riverside Medical, $21,818.29 of work, less 10% holdback, plus 5% GST, is $20,618.28 due, in CAD. The bottom line keeps the total Holdback held to date.
When the holdback period is over, bill it. Valley Fitness Center was completed on August 24, so its holdback came due on October 18. Invoice 1017 bills the Holdback released, $29,373.02, plus the GST on it, and it was paid on November 3. Now Valley shows no holdback held.
6What can go wrong, and how to fix it

A deadline is close and the job still owes money. Click Deadline in 15 days. Cedar Park owes $101,907.48 with 15 days left. Call the general contractor now, and talk to your lawyer about filing a lien before the deadline, not after.
The completion date is wrong. Click Completion and fix the last day of work. The deadline and the release date move with it.
The holdback percent is wrong for a job. Change it on the next invoice, or for every new invoice in Accounting settings. Invoices already sent keep what they printed.
Worked example: Northgate’s five BC jobs on November 19
The Holdback and liens page on November 19, 2026:
| Job | Holdback held | Lien deadline | Due back |
|---|---|---|---|
| Valley Fitness Center | $0.00 | paid | released |
| Lincoln Elementary | $39,984.76 | paid | Nov 20 |
| Cedar Park Senior Living | $35,946.20 | Dec 4, 15 days | Dec 14 |
| Oakmont Tech Campus | $33,262.06 | Dec 14, 25 days | Dec 24 |
| Riverside Medical Office | $41,454.77 | Dec 29, 40 days | Jan 8 |
| Total held | $150,647.79 |
One call this week, to Cedar Park, and one holdback to bill tomorrow, for Lincoln.
What to do next
Next, see the GST you owe each quarter in GST and PST at the end of each quarter.
Know every holdback and lien deadline
Holdback and liens is part of CFE BidWise Business. Start with the 30-day free trial, no credit card.
Frequently Asked Questions
Does CFE BidWise file the lien for me?
No. It counts the days and shows which jobs are close. Filing a lien is done with the land title office, usually through a lawyer. The page is a reminder list, not legal advice.
Is the GST charged on the holdback?
CFE BidWise takes the holdback off before the GST on each progress invoice, and charges the GST on the holdback when you bill its release.
Which provinces does it know?
Every province and territory. The province in Settings › Company info sets the holdback percent, the lien days and the holdback period, and you can change them in Accounting settings.