Job Labor Budget in Crew Days

Pick a job and a crew, and the Job labor budget shows what the bid’s man days cost with your own crew. Here 31.89 man days on a 3-man crew is 10.63 crew days. At $1,087.68 a day that is a budget of $11,562.04 at standard wage, or $17,174.68 at prevailing. The estimate priced $43,693.35 of labor, so there is $32,131.31 of room.

  • 4 minutes
  • Intermediate
  • CFE BidWise Business
CFE BidWise Job labor budget for Lincoln Elementary Modernization: 31.89 man days, 10.63 crew days, budget $11,562.04, covered with room $32,131.31
Video walkthrough · 3:42 · Guide 93 of 100

Why a labor budget?

The estimate prices labor at a rate per unit. Your crew is paid by the day. Until you turn one into the other, you do not know if the job makes money on labor.

The Job labor budget does it for you, with the real loaded cost of the crew that will install it.

The five steps

  1. Open the budgetPick the job, crew and wage.
  2. Man days to crew days31.89 man days = 10.63 crew days.
  3. Against the estimateRoom left on labor.
  4. The crew behind itWho, their rate, their day.
  5. What can go wrongNo man days, or the wrong crew.

1Open the Job labor budget

CFE BidWise Job labor budget: job JR-260102 Lincoln Elementary Modernization, crew Crew A Marco, wage standard or prevailing
Pick the job, the crew, and Standard or Prevailing.

In Accounting › In-House Pay, click Job labor budget (Standard / PW). Pick the Job, here JR-260102, Lincoln Elementary Modernization, and the Crew, Crew A, Marco.

The Wage starts from the job: this is a Standard wage job. Click Prevailing wage (PW) to see the same job at prevailing rates.

2Turn man days into crew days

CFE BidWise Job labor budget: bid man days divided by 3-man crew, 31.89 man days = 10.63 crew days, one crew day with burden $1,087.68 standard and $1,615.68 prevailing, labor budget $11,562.04 and $17,174.68
31.89 man days = 10.63 crew days, at $1,087.68 a day.

Bid man days ÷ 3-man crew: the bid has 31.89 man days, so 10.63 crew days. One crew day, 8 hours with burden, is $1,087.68 at standard wage and $1,615.68 at prevailing.

The Labor budget for the job is 10.63 × $1,087.68 = $11,562.04 at standard wage, and $17,174.68 at prevailing.

3Compare it with the labor the estimate priced

CFE BidWise Job labor budget: labor the estimate priced $43,693.35, covered with room at standard wage $32,131.31, prevailing wage adds $5,612.64 to this job
Labor priced $43,693.35; covered, with $32,131.31 of room.

Labor the estimate priced is $43,693.35. Against the standard wage budget, the job is Covered, with room: $32,131.31.

The line below says what prevailing wage would do: it adds $5,612.64 to this job’s crew labor, $528 a crew day.

Quick Tip

Look at the room before you book the install. If the room is thin, book the crew with the fewest apprentices, or plan the job so it does not run into overtime.

4See the crew behind the number

CFE BidWise Crew A Marco standard wage: Marco Silva lead foreman, Andre Silva journeyman, Kevin Tran apprentice 70%, burden 32%, loaded $55.44, $47.52, $33.00, one day $443.52, $380.16, $264.00
Crew A: each installer, the burden, loaded $/hr and one day.

Below, Crew A · Marco · Standard wage shows the people behind the crew day: Marco, foreman, $55.44 loaded and $443.52 a day; Andre, journeyman, $380.16; Kevin, apprentice at 70%, $264.00.

The crew mix line says 1 foreman, 1 journeyman, 1 apprentice, a 2:1 ratio of journey-level to apprentice. Click Print for the job file.

5What can go wrong, and how to fix it

CFE BidWise crew mix: 1 foreman, 1 journeyman, 1 apprentice, ratio 2:1 journey-level to apprentice, internal pay rates are confidential, Accounting only
The crew mix, and pay kept confidential.

Crew days show 0. The bid has no man days. Open the estimate and check the labor lines.

The budget is for the wrong crew. Pick the crew that will really install it. A crew with two apprentices costs less per day.

The wage is wrong. A public job should show Prevailing. Set Prevailing Wage = Yes on the estimate.

Worked example: Lincoln Elementary

JR-260102, Lincoln Elementary Modernization, Crew A:

LineStandard wagePrevailing wage
Crew days10.6310.63
One crew day$1,087.68$1,615.68
Labor budget$11,562.04$17,174.68
Labor the estimate priced$43,693.35$43,693.35
Room$32,131.31$26,518.67

Even at prevailing wage, the labor on this job is covered.

What to do next

Next: see where every Won job is, from the Dashboard.

Know the labor budget before the crew starts

The job labor budget is part of CFE BidWise Business. Start with the 30-day free trial, no credit card.

Download Free for Windows64-bit · 30-day free trial · no credit card

Frequently Asked Questions

Where do the man days come from?

From the bid’s labor lines. They are divided by the men in a crew under Settings, Installers.

Is this payroll?

No. It is for budgeting the job. Payroll stays in your payroll system.

Who can see it?

Only the Master user with the Accounting password. Pay rates are confidential.

Cristian Valcu, founder of Commercial Flooring Estimating LLC

Written by

Cristian Valcu – Founder & CEO, Commercial Flooring Estimating LLC

Cristian has estimated commercial flooring for over 20 years and built CFE BidWise around the way flooring contractors actually price, propose and track their bids.