Bill the Uncertified Amount on the Next Pay App

Make the next progress invoice as usual. If the GC certified less on the last application and you ticked bill the difference on the next one, the line Not certified on INV-1005, billed again is added by itself. The invoice, the G702 (line 8) and the print all show it, and the first pay app says Billed again on INV-1006, so the amount is counted only once.

  • 5 minutes
  • Intermediate
  • CFE BidWise Business
CFE BidWise pay app 2 G702 for Lincoln Elementary Modernization: current payment due $103,417.68, includes $13,451.98 not certified on application 1, billed again
Video walkthrough · 4:54 · Guide 104 of 110

Why bill it on the next application?

Most GCs will not pay a line twice on the same application, but they expect the contractor to bill the work again next month, once it is accepted. The risk is on your side: if the next pay app is built from the percent complete only, the cut amount quietly disappears.

BidWise carries it as its own line, with the invoice it came from, so the GC sees exactly what is billed again and why.

The six steps

  1. Make the next invoiceProgress billing, % complete.
  2. Check the invoiceIt prints as its own line.
  3. Pay app #2, line 8The note under the payment due.
  4. Print or save itG702 and G703, one page.
  5. Counted only onceBilled again on INV-1006.
  6. What can go wrongNo line, wrong amount.

1Make the next progress invoice

CFE BidWise new invoice INV-1006 progress billing for Lincoln Elementary Modernization: base bid $399,847.56, 60% complete to date, this invoice $99,961.89, billed to date $239,908.54
Base bid 60% complete: $99,961.89 this invoice.
CFE BidWise This invoice: work this period $99,961.89, retainage held 10% minus $9,996.19, not certified on INV-1005 billed again $13,451.98, amount due $103,417.68
Not certified on INV-1005, billed again: $13,451.98.

Click New invoice on the Invoicing tab and pick the job. Lincoln Elementary’s second invoice, INV-1006, is Progress billing: type the percent complete to date, here 60%, and This invoice is $99,961.89.

On the right, This invoice shows the work this period, less 10% retainage, and one more line, added by itself: Not certified on INV-1005, billed again, $13,451.98. The amount due is $103,417.68.

2Check the invoice before you send it

CFE BidWise invoice INV-1006 as it prints: work this period $99,961.89, less retainage 10%, not certified on application 1 INV-1005 billed again $13,451.98, amount due $103,417.68
The printed invoice: not certified on application #1, billed again.

Click Preview. The invoice prints the line under the retainage: Not certified on application #1 (INV-1005), billed again, $13,451.98, and the Amount due, $103,417.68.

The GC sees where the amount came from without a phone call. Send it with Send now, or save the PDF.

3See it on pay app #2, line 8

CFE BidWise G702 application 2: total completed $239,908.54 60%, retainage $23,990.86, total earned less retainage $215,917.68, less previous certificates $112,500.00, current payment due $103,417.68, includes $13,451.98 not certified on application 1 billed again
Line 7 uses what the GC certified, $112,500. Line 8 notes the $13,451.98.

Open Pay app (G702). Application #2 is made from INV-1006. Line 6, total earned less retainage, is $215,917.68. Line 7, Less previous certificates for payment, is $112,500.00, what the GC really certified last time, not what you asked for.

So line 8, Current payment due, is $103,417.68, and the note under it says it includes $13,451.98 not certified on application #1, billed again.

Quick Tip

Line 7 should always match the GC’s certificates, not your own invoices. If the GC’s math and yours differ on line 7, every application after it will be off too.

4Print or save the pay app

CFE BidWise Print Preview of pay app 2, G702 and G703, with the note under line 8: includes $13,451.98 not certified on application 1, billed again
Print Preview: the note prints under line 8.

Click Print Preview. The G702 summary and the G703 continuation sheet print together, and the note under line 8 prints with them.

Click Print or Save PDF, and send it the way the GC wants it.

5Check that it is counted only once

CFE BidWise pay app 1 GC approval: approved for less, certified $112,500.00, $13,451.98 less, billed again on INV-1006
Pay app #1 now says: Billed again on INV-1006.
CFE BidWise Job billing for Lincoln Elementary: contract $399,847.56, billed to date $239,908.54, paid $0.00, owed now $215,917.68, retainage held $23,990.86, left to bill $159,939.02
Job billing: owed now $215,917.68, counted once.

Go back to pay app #1. Its GC approval box now says, in green, Billed again on INV-1006, so nobody bills the same $13,451.98 a third time.

In Job billing, Owed now is $215,917.68: $112,500 on application #1 plus $103,417.68 on application #2. The short pay is in there once.

6What can go wrong, and how to fix it

CFE BidWise GC approval application 1: approved for less, certified $112,500.00, goes on the next application
No billed-again line? Check the GC answer on the last pay app.

The billed-again line is not on the new invoice. The GC answer on the last pay app was not saved, or bill the difference on the next application was not ticked. Open the last pay app, fix the GC answer, then make the invoice.

The amount is wrong. It comes from the amount certified. Fix the GC answer while the new invoice is still a draft.

The GC cut it again. Type the new GC answer on pay app #2, and the difference goes on #3.

Worked example: Lincoln Elementary, application #2

INV-1006, November 20, 2026:

LineAmount
Work this period, 60% to date$99,961.89
Less retainage 10%−$9,996.19
Not certified on #1, billed again$13,451.98
Amount due$103,417.68

The GC sees the $13,451.98 again, on its own line, with the invoice it came from.

What to do next

Next, see every salesman’s bids, wins and commission in Salesmen reports.

Bill every dollar the GC owes

Pay apps are part of CFE BidWise Business. Start with the 30-day free trial, no credit card.

Download Free for Windows64-bit · 30-day free trial · no credit card

Frequently Asked Questions

Does BidWise add the billed-again line by itself?

Yes, when the GC answer on the last pay app is Approved for less and bill the difference on the next application is ticked.

Where does it show on the G702?

As a note under line 8, Current payment due. Line 7 uses the amount the GC certified.

Can it be billed twice?

No. The first pay app says Billed again on the new invoice, and Job billing counts it once.

Cristian Valcu, founder of Commercial Flooring Estimating LLC

Written by

Cristian Valcu – Founder & CEO, Commercial Flooring Estimating LLC

Cristian has estimated commercial flooring for over 20 years and built CFE BidWise around the way flooring contractors actually price, propose and track their bids.